Orange Projects - Renovations & Carpentry
Home Renovations South East Queensland 11 min read

Renovation Timeline: How Long Does a Renovation Actually Take?

Renovation in progress on a Gold Coast home showing framing and new openings

Quick answer: a kitchen renovation typically takes 3 to 14 days on site, a bathroom 3 to 4 weeks, a deck 1 to 3 weeks, a full home renovation 4 to 16 weeks and a ground-floor extension 4 to 8 months including approvals. Add three to eight weeks of design, approval and procurement before any on-site work begins.

The two clocks in every renovation

Homeowners think about build time. Builders think about two clocks: the pre-construction clock and the on-site clock. Pre-construction covers measure-up, design, engineering, certification, selections and lead times on cabinetry, stone, windows and tiles. On-site is the visible part. Projects that feel slow are usually projects where pre-construction was rushed, so the site waits on decisions.

Typical durations by project type

  • Kitchen renovation - 3 to 14 days on site, after 4 to 8 weeks for joinery and stone
  • Bathroom renovation - 3 to 4 weeks, driven by waterproofing cure times and tiling
  • Laundry renovation - 1 to 2 weeks
  • Flooring replacement, whole house - 3 to 6 days plus acclimatisation
  • Timber or composite deck, 30 sqm - 1 to 3 weeks
  • Internal wall removal with beam - 1 to 2 weeks including make-good
  • Feature or media wall - 3 to 7 days
  • Full home renovation - 4 to 16 weeks
  • Garage conversion - 4 to 8 weeks
  • Ground-floor extension - 12 to 20 weeks on site
  • Second-storey addition - 20 to 32 weeks on site

A realistic week-by-week: full home renovation

  1. Weeks 1-2: site set-up, protection, strip-out and any licensed asbestos removal
  2. Weeks 2-4: structural works - beams, new openings, framing, subfloor corrections
  3. Weeks 4-6: services rough-in and frame inspection
  4. Weeks 6-7: insulation, linings, set and sand
  5. Weeks 7-9: waterproofing and certification, then wet-area tiling
  6. Weeks 9-11: cabinetry install, benchtop template and install, flooring
  7. Weeks 11-13: carpentry finishes, doors, skirting, architraves
  8. Weeks 13-15: painting, fit-off, electrical and plumbing final
  9. Week 15-16: clean, certifier final, defect walk-through, handover

Planning work on the Gold Coast or in Brisbane? Talk to a QBCC-licensed team (Licence No. 15620733) and get a fixed-price quote after a proper site inspection.

Get an initial estimate

The five real causes of delay

  1. Late selections - a benchtop chosen in week six delays the entire back half of the program
  2. Approval timing - certification and any development application must be resolved before start, not during
  3. Concealed conditions - termite damage, undersized framing, hidden asbestos and non-compliant old work
  4. Client-supplied items arriving late or incorrect
  5. Weather - realistically 5 to 12 lost days per year on external work in South East Queensland, more through the summer storm season

How to compress a renovation program honestly

You cannot compress waterproofing cure times, stone fabrication or concrete curing. You can compress everything that depends on decisions. Finalise every selection before contract signing. Order long-lead items - windows, custom joinery, imported tile - the day the contract is signed. Consolidate trades so services rough-in happens in one visit. And accept a single detailed scope rather than adding variations, because each variation resets sequencing for the trades downstream of it.

Every day a decision sits unmade during construction usually costs two days on site.

Living through it

For kitchen work, set up a temporary bench with the fridge, microwave and kettle in another room and plan for takeaway during fit-off week. For bathrooms, a single-bathroom home needs a plan - most clients arrange with family or a nearby rental for the two weeks around waterproofing and tiling. For full renovations, moving out shortens the program because trades can work in parallel without protecting occupied space.

Not sure what your budget stretches to? Upload a photo of the space and our AI Renovator returns a concept and an indicative cost in about a minute.

Try the AI Renovator

Frequently asked questions

OP
Written by
Orange Projects

QBCC-licensed business delivering premium renovations, carpentry and commercial fitouts across the Gold Coast and Brisbane. Real projects, honest advice.

Ready to talk?

Get a fixed-price quote from a builder who returns your call.

We'll walk your site, listen properly, and give you a written quote you can actually compare.

Renovation newsletter

Get practical renovation and fitout advice, once a month.

Real Gold Coast and Brisbane project insights, pricing shifts and planning tips. No fluff, unsubscribe anytime.